A $488 million syndicated loan for a Malaysian data center intended for use by ByteDance has stalled as arrangers seek additional banks to join the facility.

MissedBlock Desk · 3 min read

ByteDance Malaysia Data Center Loan Hits Snag Amid AI Lending Caution

ByteDance Data Center Loan Faces Unforeseen Pause

A $488 million syndicated loan for a Malaysian data center intended for use by ByteDance has stalled as arrangers seek additional banks to join the facility. The loan briefing and site visit, originally scheduled for November 2nd, were postponed, a pause described as rare by Bloomberg.

Loan Syndication Process

Syndicated loans involve several lead banks committing to fund a loan, then selling portions of it to other financial institutions in a process known as syndication. The briefing and site visit are standard due diligence steps for potential participating banks before they commit. While lead arrangers reserve the right to adjust schedules, the simultaneous postponement of both events is unusual for Asian banking practices, where timelines are typically adhered to as per invitation.

Lead Arrangers and Project Details

The four lead arrangers – HSBC, AIIB, Sumitomo Mitsui Banking Corporation, and Bank of China – have already signed commitments to fund Epoch Digital. The reason for the delay, according to one person familiar with the matter, is a simple scheduling conflict, with Epoch Digital’s management unavailable on the originally planned dates. New briefing dates are currently being arranged.

Epoch Digital, which is almost entirely owned by funds managed by Actis, was established in November 2022. Its first project is located in Johor, Malaysia, with a data center facility. The Asian Infrastructure Investment Bank (AIIB) approved a $125 million financing for the project on April 23rd. Project documentation indicates Actis as the sponsor and Epoch Digital as the executor. The initial phase of 60MW of power capacity for servers has been fully leased to BytePlus, ByteDance’s enterprise cloud division. The overall planned capacity for the campus is 120MW, and construction is nearing completion.

New Regulatory Landscape

There is currently no indication that the loan delay is related to the new U.S. regulations announced on November 16th. The U.S. Department of Commerce’s Bureau of Industry and Security (BIS) published an interim final rule requiring export licenses for chips shipped to or transferred for use in third-country data centers that provide substantial computing power to companies headquartered in China. Malaysia is among the five countries newly subject to these export licensing requirements.

Given that the initial phase of the data center is fully leased to ByteDance, these new regulations are directly relevant to the project.

Related Developments

  • Reports suggest the U.S. is seeking to curb China’s access to overseas computing power using Nvidia chips, with seven countries including Singapore and Thailand reportedly named.
  • Malaysia’s sovereign AI tenders are leaning towards Huawei chips, potentially marking the first instance of a country globally choosing Chinese over U.S. technology.
  • AI cloud provider Nscale’s IPO is facing hurdles, with investors deeming its $30 billion valuation too high.
  • Nvidia’s default risk has risen to near-historic highs, increasing by over three times since mid-year, with the board reportedly discussing CEO Jensen Huang’s tenure.
  • Morgan Stanley notes that AI infrastructure development is being hampered by “people, power, and politics,” with the U.S. facing a power deficit exceeding 30% by 2028.